River Corridor Redevelopment Plan

Next Steps

October 2008 Developer Skogman will kick off new housing construction in October 2008, with housing availability 2009.

Early November 2008 City Council takes action on River Corridor Framework for Reinvestment & Revitalization.

December 2008 Neighborhood planning process unveiled, which will last from Early ’09 to Summer ’09.

Late 2008 Army Corps of Engineers begins its Flood Management Strategy feasibility analysis, projected to take 19 to 24 months, likely to conclude in 2010.

2009 Planning and development City/Community facilities.

2009 Kickoff of feasibility determination for first downtown projects - cornerstone of downtown reinvestment and redevelopment.

2009 Kickoff of multi-family housing construction.

2010–2015 Community facilities construction.

2012 Flood management system construction begins.